Collection System Improvements Contract 2 - Week of July 7th

Purpose of Project:
Rehabilitation of approximately 4,700 linear feet of combined sewers, manholes and service connection in the Cities of Union City and West New York.

Key Phases & Timeline

  • Late February, contractor mobilize to Park Avenue Siphon Chamber

Work Period & Location

  • Daytime work 8am to 4pm:

    • 7/7 - 216 42nd Street to 131 42nd Street

  • Nighttime work 8pm to 4am:

    • 07/8/25-07/9/25 - 146 35TH STREET to 218 35th street

    • 07/8/25-07/9/25 - 607 12TH STREET to 527 12th street

    • 07/9/25-07/10/25 - 521 12TH ST to 426 12th street,

    • 07/9/25-07/10/25 - 426 12th street to 1213 Bergenline ave

    • 7/10/25 - 3507 park avenue to 108 35th street

    • 7/10/25 - 101 34th street to 108 34th St

Description of Work

  • Sewer lining

Traffic Information:

  • Road Closures: Police will be onsite to close the streets if needed.

  • Parking Restrictions: None

  • Detours: None

  • Police presence: Yes

  • Noise/Disruptions: Sewer lining could produce some short duration noise.

We appreciate your patience and cooperation as we work to improve our infrastructure. Stay tuned for further updates!