NHSA Weehawken Infrastructure Project: June 23rd - July 4th

Purpose of Project:
The Township of Weehawken has hired Underground Utilities Corporation to repair sidewalks and roads where stormwater sewer work was previously done.

Work Location:

  • Hamilton Ave – from Blvd East to King Ave

Description of Work:

  • Resetting of the paver sidewalk in front of 1 Hamilton and placing topsoil and seeding in areas that have been slightly disturbed by new sidewalk construction.

  • Resetting the paver sidewalk in front of 1 Hamilton and placing topsoil.

Traffic Information:

  • Hamilton Ave will be closed to through traffic.

  • There will be no parking on Hamilton Ave in the vicinity of the work zone between Blvd East and King Ave.

  • Traffic signs to be posted as necessary.

We appreciate your patience and cooperation as we work to improve our infrastructure. Stay tuned for further updates!