NHSA Blvd East - Sidewalk and Pavement Restoration: July 28th - August 1st

Purpose of Project:
The Township of Weehawken has hired Underground Utilities Corporation to repair sidewalks and roads where stormwater sewer work was previously done.

Work Location:

  • Hamilton Ave (from Blvd East to King Ave)

  • Highwood Ave (from Blvd East to El Dorado Place)

  • Blvd East (Northbound)

  • Burr Place

Description of Work:

  • Operator training at the pump station (pump controls & generator) for NHSA O&M staff

  • Manhole rehabilitation in front of 163 Highwood Ave (no demolition or heavy equipment)

  • General cleanup at the pump station

  • Tentative: CCTV inspections of newly installed sewer pipe (coordination with Weehawken PD and no parking signage along Blvd East, Highwood Ave, and Hamilton Ave)

Traffic Information:

  • Temporary street closures (up to 8 hours)

  • No parking on Hamilton Ave between Blvd East and King Ave during work

  • Hamilton Ave will be closed to through traffic during pavement and curb work

  • Traffic signs will be posted as necessary

We appreciate your patience and cooperation as we work to improve our infrastructure. Stay tuned for further updates!

Previous
Previous

NHSA H6/H7 Hoboken Phase 2 Construction and Traffic Management Activities: July 28th – August 1st, 2025

Next
Next

Madison Street Infrastructure Improvements: Construction and Traffic Management Activities July 28th - August 1st