NHSA H6/H7 Hoboken Phase 3 Construction and Traffic Management Activities: December 22 - December 26, 2025

Project Overview
The goal of the project is to reduce combined sewer overflows (CSO’s) and improve the water quality of the Hudson River. As part of the project, new storm sewer lines and curb inlets will be installed which will alleviate drainage and potential flooding issues in the northern H6 and H7 drainage basins in Hoboken.

Key Phases & Timeline

  • Monday, December 22 to Friday, December 26, 2025

Construction Activities:

Holiday:

December 25 -26:  Christmas Holiday; No Scheduled Work

Pipeline Crew #1:

  •  Grand Street between 14th Street and 15th Street

    • Installation of piles, pile caps, and pipe cradles

    • Installation of storm sewer pipe, manholes, and inlets

Pipeline Crew #2:

Clinton Street between Grand Street and Clinton Street

  • Installation of piles, pile caps, and pipe cradles

  • Installation of storm sewer pipe, manholes, and inlets

Pipeline Crew #3:

15th Street and Clinton Street Intersection

  • 16" and 8" water main relocation

Traffic Management:

Grand Street between 13th and 14th Street

  • Road open to traffic

  • Roadway changed to 2-Way traffic (north and south) to allow access to resident garages.

Grand Street between 14th and 15th Street

  • Road open; however, closed within construction area only (24 hours, 7 days/week)

  • Roadway changed to 2-Way traffic (north and south) to allow access to resident garages.

Clinton Street between 14th and 15th Street

  • Road open; however, closed mid-block within construction area only (24 hours, 7 days/week)

  • Roadway is 2-Way traffic (north and south) to allow access to resident garages.

14th Street between Grand Street and Clinton Street

  • Road to be closed 24 hours, 7 days/week

  • Access provided to local residents and KL Masters only

15th Street and Clinton Street Intersection

  • Road open to traffic

  • 15th Street will be alternating traffic

Temporary Parking Impacts:

Grand Street between 13th and 14th Street

  • East side:  No parking (24/7)

Grand Street between 14th and 15th Street

  • West and East side:  No parking (24/7) 

Clinton Street between 14th Street and 15th Street

  • West and East side:  No parking (24/7)

13th Street between Adams Street and Grand Street

  • No parking both sides (6 am to 6 pm)

15th Street and Clinton Street Intersection

  • Temporary no parking both sides of the both streets – 70’ in all directions (6am - 6 pm)

    We appreciate your patience and cooperation as we work to improve our infrastructure.

Previous
Previous

NHSA H6/H7 Hoboken Phase 2 Construction and Traffic Management Activities: Week of December 22nd - December 26th

Next
Next

NHSA H6/H7 Hoboken Phase 2 Construction and Traffic Management Activities: Week of December 15th - December 19th