NHSA H6/H7 Hoboken Phase 3 Construction and Traffic Management Activities: January 5th - January 9th, 2026

Project Overview
The goal of the project is to reduce combined sewer overflows (CSO’s) and improve the water quality of the Hudson River. As part of the project, new storm sewer lines and curb inlets will be installed which will alleviate drainage and potential flooding issues in the northern H6 and H7 drainage basins in Hoboken.

Key Phases & Timeline

  • Monday, January 5th - January 9th, 2026,

Construction Activities:

Pipeline Crew #1:

Grand Street and 15th Street Intersection

  • Installation of piles, pile caps, and pipe cradles for the Depressed Sewer

  • Installation of storm sewer pipe, manholes, and inlets

 

Pipeline Crew #2:

Clinton Street between 14th Street and 15th Street

  • Installation of piles, pile caps, and pipe cradles

  • Installation of storm sewer pipe, manholes, and inlets

Traffic Management:

 Grand Street and 15th Street Intersection

  • Road open to traffic along 15th Street

Grand Street between 13th and 14th Street

  • Road open to traffic

  • Roadway changed to 2-Way traffic (north and south) to allow access to resident garages.

Grand Street between 14th and 15th Street

  • Road open; however, closed within construction area only (24 hours, 7 days/week)

  • Roadway changed to 2-Way traffic (north and south) to allow access to resident garages.

Clinton Street between 14th and 15th Street

  • Road open; however, closed mid-block within construction area only (24 hours, 7 days/week)

  • Roadway is 2-Way traffic (north and south) to allow access to resident garages.

14th Street between Grand Street and Clinton Street

  • Road to be closed 24 hours, 7 days/week

  • Access provided to local residents and KL Masters only

Temporary Parking Impacts:

Grand Street between 13th and 14th Street

  • East side: No parking (24/7)

  • Grand Street between 14th and 15th Street

    • No parking both sides (24/7)

  • Clinton Street between 14th Street and 15th Street

    • No parking both sides (24/7)

  • 15th Street and Grand Street Intersection

    • Temporary no parking both sides of the both streets – 100’ in all directions (24/7)

  • 13th Street between Adams Street and Grand Street

    • North side: No parking (6 am to 6 pm)

We appreciate your patience and cooperation as we work to improve our infrastructure.