NHSA H6/H7 Hoboken Phase 3 Construction and Traffic Management Activities: Monday, March 16 - Friday, March 20, 2026
Project Overview
The goal of the project is to reduce combined sewer overflows (CSO’s) and improve the water quality of the Hudson River. As part of the project, new storm sewer lines and curb inlets will be installed which will alleviate drainage and potential flooding issues in the northern H6 and H7 drainage basins in Hoboken.
Key Phases & Timeline
The following construction activities and traffic management are anticipated to take place from Monday, March 16 to Friday, March 20, 2026, by the NHSA - H6/H7 Phase 3 Project:
Construction Activities:
Pipeline Crew #1:
Clinton Street between 15th Street and 16th Street
Installation of piles, pile caps, and pipe cradles
Installation of storm sewer pipe, manholes, and inlets
Pipeline Crew #2:
16th Street between Clinton Street and Willow Street
Installation of piles and pile caps
Installation of storm sewer pipe, manholes, and inlets
Restoration Crews:
14th Street between Grand Street and Clinton
Sidewalk and Curb restoration
16th Street and Adams Street Intersection
Sidewalk and Curb restoration
16th Street and Jefferson Street
Sidewalk and Curb restoration
15th Street and Clinton Street
Sidewalk and Curb restoration
Traffic Management:
Clinton Street between 15th Street and 16th Street
Road to be closed 24 hours, 7 days/week
Grand Street between 13th and 14th Street
Road open to traffic
Roadway changed to 2-Way traffic (north and south) to allow access to resident garages.
14th Street between Grand Street and Clinton Street
Road to be closed 24 hours, 7 days/week
Access provided to local residents and KL Masters only
16th Street between Clinton Street and Willow Street
Road closed to traffic (8 am to 6 pm) and road open to traffic (6 pm to 8 am)
Access provided to local residents and businesses
Traffic detoured westbound on 16th Street
Temporary Parking Impacts:
Grand Street between 13th and 14th Street
East side: No parking (24/7)
13th Street between Adams Street and Grand Street
North side: No parking (6 am to 6 pm)
Clinton Street between 15th Street and 16th Street
Temporary no parking both sides of 15th Street (24/7)
16th Street and Adams Street Intersection
Temporary no parking both sides of Adams Street - 100 feet all directions of intersection
16th Street between Clinton Street and Willow Street
Temporary no parking both sides of 16th Street (24/7)
16th Street and Jefferson Street Intersection
Temporary no parking both sides of Jefferson Street - 100 feet all directions of intersection
15th Street and Clinton Street - SW Corner
Temporary no parking - 70 feet South and West of the Southwest corner of intersection
We appreciate your patience and cooperation as we work to improve our infrastructure.