NHSA H6/H7 Hoboken Phase 3 Construction and Traffic Management Activities: Monday, March 16 - Friday, March 20, 2026

Project Overview
The goal of the project is to reduce combined sewer overflows (CSO’s) and improve the water quality of the Hudson River. As part of the project, new storm sewer lines and curb inlets will be installed which will alleviate drainage and potential flooding issues in the northern H6 and H7 drainage basins in Hoboken.

Key Phases & Timeline

  • The following construction activities and traffic management are anticipated to take place from Monday, March 16 to Friday, March 20, 2026, by the NHSA - H6/H7 Phase 3 Project:

Construction Activities:

Pipeline Crew #1:

Clinton Street between 15th Street and 16th Street

  • Installation of piles, pile caps, and pipe cradles

  • Installation of storm sewer pipe, manholes, and inlets

Pipeline Crew #2:

16th Street between Clinton Street and Willow Street

  • Installation of piles and pile caps

  • Installation of storm sewer pipe, manholes, and inlets

Restoration Crews:  

14th Street between Grand Street and Clinton

  •   Sidewalk and Curb restoration

16th Street and Adams Street Intersection

  • Sidewalk and Curb restoration

16th Street and Jefferson Street

  • Sidewalk and Curb restoration

15th Street and Clinton Street

  • Sidewalk and Curb restoration

Traffic Management:

Clinton Street between 15th Street and 16th Street

  • Road to be closed 24 hours, 7 days/week

Grand Street between 13th and 14th Street

  • Road open to traffic

  • Roadway changed to 2-Way traffic (north and south) to allow access to resident garages.

14th Street between Grand Street and Clinton Street

  • Road to be closed 24 hours, 7 days/week

  • Access provided to local residents and KL Masters only

16th Street between Clinton Street and Willow Street

  • Road closed to traffic (8 am to 6 pm) and road open to traffic (6 pm to 8 am)

  • Access provided to local residents and businesses

  • Traffic detoured westbound on 16th Street

Temporary Parking Impacts:

Grand Street between 13th and 14th Street

  • East side: No parking (24/7)

13th Street between Adams Street and Grand Street

  • North side: No parking (6 am to 6 pm)

Clinton Street between 15th Street and 16th Street

  •  Temporary no parking both sides of 15th Street (24/7)

16th Street and Adams Street Intersection

  • Temporary no parking both sides of Adams Street - 100 feet all directions of intersection

16th Street between Clinton Street and Willow Street

  • Temporary no parking both sides of 16th Street (24/7)

16th Street and Jefferson Street Intersection

  • Temporary no parking both sides of Jefferson Street - 100 feet all directions of intersection

15th Street and Clinton Street - SW Corner

  • Temporary no parking  - 70 feet South and West of the Southwest corner of intersection

We appreciate your patience and cooperation as we work to improve our infrastructure.

Previous
Previous

NHSA H6/H7 Hoboken Phase 2 Construction and Traffic Management Activities: Week of March 16, 2026

Next
Next

NHSA H6/H7 Hoboken Phase 2 Construction and Traffic Management Activities: Week of March 9, 2026