NHSA H6/H7 Hoboken Phase 3 Construction and Traffic Management Activities: Monday, March 23 to Friday, March 27, 2026

Project Overview
The goal of the project is to reduce combined sewer overflows (CSO’s) and improve the water quality of the Hudson River. As part of the project, new storm sewer lines and curb inlets will be installed which will alleviate drainage and potential flooding issues in the northern H6 and H7 drainage basins in Hoboken.

Key Phases & Timeline

  • The following construction activities and traffic management are anticipated to take place from Monday, March 23 to Friday, March 27, 2026, by the NHSA - H6/H7 Phase 3 Project:

Construction Activities:

Pipeline Crew #1:

Clinton Street between 15th Street and 16th Street

  • Installation of piles, pile caps, and pipe cradles

  • Installation of storm sewer pipe, manholes, and inlets

16th Street between Clinton Street and Willow Street

  • Installation of piles and pile caps

  • Installation of storm sewer pipe, manholes, and inlets

Pipeline Crew #2:

13th Street between Adams Street and Clinton Street

  • Installation of piles, pile caps, pipe cradles, and structures

  • Installation of storm sewer pipe, manholes, and inlets

Restoration Crews:

14th Street between Grand Street and Clinton

  •   Sidewalk and Curb restoration

16th Street and Adams Street Intersection

  • Sidewalk and Curb restoration

16th Street and Jefferson Street

  • Sidewalk and Curb restoration

15th Street and Clinton Street

  • Sidewalk and Curb restoration

Traffic Management:

Clinton Street between 15th Street and 16th Street

  • Road to be closed 24 hours, 7 days/week

Grand Street between 14th and 12th Street

  • Road closed to thru traffic, local traffic only (8 am to 6 pm)

  • Roadway changed to 2-Way traffic (north and south) on Grand Street between 14th to 13th Street to allow access to resident garages.

14th Street between Grand Street and Clinton Street

  • Road to be closed 24 hours, 7 days/week

  • Access provided to local residents and KL Masters only

16th Street between Clinton Street and Willow Street

  • Road closed to traffic (8 am to 6 pm) and road open to traffic (6 pm to 8 am)

  • Access provided to local residents and businesses

  • Traffic detoured westbound on 16th Street

13th Street between Adams Street and Grand Street

  • Road closed to thru traffic, local traffic only (8 am to 6 pm)

  • Access to 13th Street parking garages and local residents will be accessed from Adams Street

13th Street between Grand Street and Clinton Street

  • Road closed to thru traffic, local traffic only (8 am to 6 pm)

  • Access to 13th Street parking garages and local residents will be accessed from Clinton Street

13th Street between Clinton Street and Willow Avenue

  • Roadway changed to 2-Way traffic (east and west) on 13th Street between Clinton Street and Willow Avenue

  • Road open to traffic

Temporary Parking Impacts:

Grand Street between 13th and 14th Street

  • East side: No parking (24/7)

  • West side:  Temporary no parking (24/7); 150 feet north of 13th Street and Grand intersection

Grand Street between 13th and 12th Street

  • East and West side:  Temporary no parking (24/7); 150 feet South of 13th Street and Grand intersection

13th Street between Adams Street and Willow Avenue

  • Temporary No parking both sides of 13th Street (24/7)

Clinton Street between 15th Street and 16th Street

  •  Temporary no parking both sides of 15th Street (24/7)

16th Street between Clinton Street and Willow Street

  • Temporary no parking both sides of 16th Street (24/7)

We appreciate your patience and cooperation as we work to improve our infrastructure.