NHSA H6/H7 Hoboken Phase 3 Construction and Traffic Management Activities: Monday, May 25 to Saturday, May 30, 2026

Project Overview
The goal of the project is to reduce combined sewer overflows (CSO’s) and improve the water quality of the Hudson River. As part of the project, new storm sewer lines and curb inlets will be installed which will alleviate drainage and potential flooding issues in the northern H6 and H7 drainage basins in Hoboken.

Key Phases & Timeline

  • The following construction activities and traffic management are anticipated to take place from Monday, May 25, to Saturday, May 30, 2026 by the NHSA - H6/H7 Phase 3 Project:

Construction Activities:

Construction Activities:

13th St between Clinton St and Willow Ave

  • Installation of sanitary sewer and manhole

16th St and Clinton St Intersection

  • Sewer pipe repair (weather permitting)

Restoration Activities:

Grand St between 13th St and 15th St

  • Sidewalk and curb restoration

13 St between Adams St and Grand St

  • Sidewalk and curb restoration

14th St between Grand St and Clinton St

  • Installation of cobblestone roadway

15th St and Clinton St Intersection

  • Sidewalk and curb restoration

Traffic Management:

13th St between Clinton St and Willow Ave

  • Road closed to thru traffic, open to local traffic (8 am to 6 pm)

14th St between Grand St and Clinton St

  • Road closed 24 hours, 7 days/week

  • Access provided to local residents and KL Masters

Temporary Parking Impacts:

13th St between Adams St and Willow Ave

  • No parking on both sides of 13th Street (24/7)

Grand St between 13th St and 14th St

  • No parking on both sides of Grand Street (24/7)

We appreciate your patience and cooperation as we work to improve our infrastructure.