NHSA H6/H7 Hoboken Phase 3 Construction and Traffic Management Activities: December 8th - December 12, 2025
Project Overview
The goal of the project is to reduce combined sewer overflows (CSO’s) and improve the water quality of the Hudson River. As part of the project, new storm sewer lines and curb inlets will be installed which will alleviate drainage and potential flooding issues in the northern H6 and H7 drainage basins in Hoboken.
Key Phases & Timeline
Monday, December 8 to Friday, December 12, 2025
Construction Activities:
Pipeline Crew #1:
Grand Street between 14th Street and 15th Street
Installation of piles, pile caps, and pipe cradles
Installation of storm sewer pipe, manholes, and inlets
Pipeline Crew #2:
14th Street between Grand Street and Clinton Street (including intersections)
Installation of piles, pile caps, and pipe cradles
Installation of storm sewer pipe, manholes, and inlets
15th Street and Clinton Street Intersection:
16" water main relocation and valve installation
Preparation work to be conducted Monday and Tuesday
Valve cut-in Wednesday evening / Thursday morning
Restoration Crews :
Jefferson Street and 14th Street - Jefferson St remains open
Sidewalk and Curb Restoration
Traffic Management:
Grand Street between 13th and 14th Street
Road open to traffic
Roadway changed to 2-Way traffic (north and south) to allow access to resident garages.
Grand Street between 14th and 15th Street
Road open; however, closed mid-block within construction area only (24 hours, 7 days/week)
Roadway changed to 2-Way traffic (north and south) to allow access to resident garages.
14th Street between Grand Street and Clinton Street
Road to be closed 24 hours, 7 days/week
15th Street and Clinton Street Intersection
Road open to traffic
15th Street will be alternating traffic
Temporary Parking Impacts:
Grand Street between 13th and 14th Street
East side: No parking (24/7)
Grand Street between 14th and 15th Street
West and East side: No parking (24/7)
Clinton Street between 14th Street and 15th Street
Temporary no parking East side of the street, south half, from 14th St to 15th St (6am - 6 pm)
13th Street between Adams Street and Grand Street
No parking both sides (6 am to 6 pm)
15th Street and Clinton Street Intersection
Temporary no parking both sides of the both streets – 70’ in all directions (6am - 6 pm)
We appreciate your patience and cooperation as we work to improve our infrastructure.