Collection System Improvements - 3 Sewer Lining Schedule Week of November 2nd, 2026

Purpose of Project:
Rehabilitation of approximately 4,700 linear feet of combined sewers, manholes and service connection in the Cities of Union City and West New York.

Key Phases & Timeline

  • Sewer lining activities are expected to extend through the end of September 25th - October 2nd.

Description of Work

  • Clean and TV

Timing and Location:

  • 11/5 - Liberty Place between Highwood Ave and Burr Place--8am -6pm

Traffic Information:

  • Road Closures: Police will be onsite to close the streets if needed.

  • Parking Restrictions: No Parking signs on both sides of the street.

  • Detours: None

  • Police Presence: Yes; two officers

Community Impacts:

  • Noise/Disruptions: Sewer lining could produce some short duration noise.

We appreciate your patience and cooperation as we work to improve our infrastructure. Stay tuned for further updates!