Purpose of Project:
Rehabilitation of approximately 4,700 linear feet of combined sewers, manholes and service connection in the Cities of Union City and West New York.
Key Phases & Timeline
Sewer lining activities are expected to extend through the end of September 25th - October 2nd.
Description of Work
Clean and TV
Timing and Location:
11/5 - Liberty Place between Highwood Ave and Burr Place--8am -6pm
Traffic Information:
Road Closures: Police will be onsite to close the streets if needed.
Parking Restrictions: No Parking signs on both sides of the street.
Detours: None
Police Presence: Yes; two officers
Community Impacts:
Noise/Disruptions: Sewer lining could produce some short duration noise.
We appreciate your patience and cooperation as we work to improve our infrastructure. Stay tuned for further updates!