Madison Street Infrastructure Improvements: Construction and Traffic Management Activities April 21st - April 25th
Madison Street Infrastructure Improvements
The Madison Street Area Infrastructure Improvements project will help mitigate localized flooding from rain events. The project scope includes replacing existing inlets, sewers, and water lines as well as elevating roadways, curbs, and sidewalks within the area. These improvements will alleviate the primary concerns by conveying stormwater into the sewer system.
Work on the Madison Street Area Infrastructure Improvements will require parking restrictions, partial road closures, and 24-hour closure of Madison. Area residents will be kept apprised of the work and impacts on their quality of life.
The following work and traffic management activities are anticipated for Monday, April 21st through Friday, April 25th between the hours of 8 a.m. and 4 p.m.:
Work Activities:
Madison St between 10th and 11th Street
Maintain sewer bypass.
Reconnect existing sewer laterals to new sewer.
Install new fire hydrant.
Install new curb on the east side (1000 Jefferson) and west side (Shoprite) of Madison St.
Install new sidewalk on the west side (Shoprite) of Madison St.
Demo existing sidewalk at east side (1000 Jefferson) of Madison St.
Madison St between 9th and 10th Street
Demo existing roadway pavement for helical pile installation.
Start Installing Helical Piles
Test pit electrical utilities
Traffic Management:
Madison St full closure between 10th and 11th Street.
No-Parking on Madison St between 10th and 11th Street.