NHSA H6/H7 Hoboken Phase 2 Construction and Traffic Management Activities: March 10 – March 14, 2025
Project Overview
We’re continuing Phase 2 of the H6/H7 Project to enhance infrastructure reliability and improve stormwater management in Hoboken. This work will support long-term system efficiency and reduce maintenance needs.
Key Phases & Timeline
- Week of March 10 – March 14, 2025 
- Work Locations: - 13th Street between Adams and Jefferson Streets 
- Adams Street between 13th and 15th Streets 
 
Construction Activities
- Working on stairs, grating, and prepping for louvers at the NWRP Pump Station on 13th Street between Adams and Jefferson Streets 
- Restoration of granite curb, concrete curb, concrete sidewalk, and bollards under the viaduct at the intersection of 14th and Adams Streets 
- Restoration of concrete curb and sidewalk on Adams Street between 13th and 15th Streets in front of local buildings 
- Contractor will be working on excavation and placement of wet tap at 15th Street between Clinton Street and Willow Avenue, from 3/10/2025 thru 3/14/2025. Contractor estimates one week to perform the wet tap and one week to connect. The connection will take place on 3/17/2025 to 3/21/2025. 
Traffic Management
- Adams Street between 13th and 15th Streets will be closed to thru traffic, but open to thru traffic at night. 
- HPD officers will be present at all intersections. 
- 24/7 no parking signs will be in place on both sides of Adams Street between 13th and 15th Streets. 
- There may be partial impacts to the sidewalks at 13th Street between Adams and Jefferson Streets within the pump station work area. 
- 15th Street between Clinton Street and Willow Avenue will have one-way westbound thru traffic from 3/10 thru 3/14. Roadway will be open to thru traffic during weekends. 
We appreciate your patience and cooperation as we work to improve our infrastructure.