NHSA H6/H7 Hoboken Phase 2 Construction and Traffic Management Activities: June 2nd – June 6th, 2025
Project Overview
We’re continuing Phase 2 of the H6/H7 Project to enhance infrastructure reliability and improve stormwater management in Hoboken. This work will support long-term system efficiency and reduce maintenance needs.
Key Phases & Timeline
Week of June 2nd – June 6th, 2025
Work Locations:
13th Street between Adams and Jefferson Streets
Adams Street between 13th and 15th Streets
Construction Activities
Working on louvers, pump rails, platforms for electrical work, and electrical installation for the pumps at the NWRP Pump Station on 13th Street between Adams and Jefferson Streets.
Installation of curb and curb walls on the westside of Adams Street between 14th and 15th Streets. Anticipating 2 weeks to complete before moving to east side of Adams Street.
Traffic Management
Adams Street between 13th and 15th Streets will be open to thru traffic one lane going northbound.
HPD officers will be present at all intersections within work zones.
24/7 no parking signs will be in place on both sides of Adams Street between 14th and 15th Streets.
We appreciate your patience and cooperation as we work to improve our infrastructure.