NHSA H6/H7 Hoboken Phase 2 Construction and Traffic Management Activities: Week of October 27th - October 31st

Project Overview
We’re continuing Phase 2 of the H6/H7 Project to enhance infrastructure reliability and improve stormwater management in Hoboken. This work will support long-term system efficiency and reduce maintenance needs.

Key Phases & Timeline

  • Week of October 27th - 31st, 2025

  • Work Locations:

    • 13th Street between Adams and Jefferson Streets

    • Adams Street between 14th and 15th Streets

Construction Activities

  • Electrical installation and plumbing installation for the pumps at the NWRP Pump Station on 13th Street between Adams and Jefferson Streets.

  • Load bank installation on roof

  • Guarini to install sink and heater

  • Guarini to pressure test gas line

  • Guarini to hang the generator exhaust from the ceiling begin Installation

Traffic Management

  • No parking on 13th Street between Adams and Jefferson Streets between the hours of 6AM to 6PM.

We appreciate your patience and cooperation as we work to improve our infrastructure.

Previous
Previous

NHSA H6/H7 Hoboken Phase 3 Construction and Traffic Management Activities: October 27th – October 31st, 2025

Next
Next

NHSA H6/H7 Hoboken Phase 2 Construction and Traffic Management Activities: Week of October 20th - October 24th