H6/H7 CSO Long Term Control Plan Project - Phase 3 Traffic Management Activities: July 13 – July 17, 2026
Project Overview
The goal of the project is to reduce combined sewer overflows (CSO’s) and improve the water quality of the Hudson River. As part of the project, new storm sewer lines and curb inlets will be installed which will alleviate drainage and potential flooding issues in the northern H6 and H7 drainage basins in Hoboken.
Key Phases & Timeline
Work hours – 8:00am to 6:00pm
work Impact:
No parking will be in effect during milling, paving, and striping activities
Roads will be closed during milling and paving activities
Construction Activities:
Paving and Striping Activities for the project will continue and the anticipated schedule which is subject to change based on weather and progress is as follows. Streets will be closed to traffic during this work. There will also be Temporary No Parking to accommodate this work.
Monday, July 13, 8 am to 6 pm:
Roadway striping will be performed along 13th St (Adams St to Willow Ave)
The roadway will be closed during striping and re-opened once striping is completed
There will also be Temporary No Parking to accommodate this work
Note that there will be periodic curb and sidewalk restoration throughout the area however, roadways will remain open during this work.

