NHSA H6/H7 Phase 2: Construction & Traffic Management Activities, Feb 26 - Mar 1, 2024

Anticipated Construction Activities and Traffic Management for the NHSA H6/H7 Phase 2 project for the period 02/26/2024 through 03/01/2024 is as follows:

 

Construction Activities

  • Watermain relocation on Adams Street between 14th Street and 15th Street.

  • Test Pits on 15th Street between Adams and Grand Streets.

 

Traffic Management

  • Adams Street between 13th Street and 15th Street will be closed to thru traffic during the day from 2/26 thru 3/1. 

  • 2 HPD Officers will be present on site to assist in traffic redirection. One will be located at 14th, and one will be located at 15th. 

  • No parking signs will be placed on both sides of Adams Street between 13th Street and 15th Street from 2/26 thru 3/1.

  • There may be partial impacts to the sidewalks on 14th and Adams in the Work area, however, safe passage for pedestrian traffic will be provided at all times.

  • 15th Street between Grand and Adams will be two lane traffic 2/27 & 2/28. Traffic to be shifted to South Side of 15th Street. 

  • 2 HPD Officer will be present at 15th Street between Adams and Grand to assist in traffic redirection.

  • No parking signs will be placed on 15th Street from Adams Street to Grand Street on 2/27 and 2/28.

  • There may be partial impacts to the sidewalks on 15th and Adams in the Work area, however, safe passage for pedestrian traffic will be provided at all times.

Previous
Previous

North Hudson Sewerage Authority Weehawken Infrastructure Project - A Preview of the Next Two Weeks (March 4th - March 15th, 2024)

Next
Next

North Hudson Sewerage Authority Weehawken Infrastructure Project Two Week Look Ahead For 2/26 - 3/8/2024