NHSA H6/H7 Phase 2: Construction and Traffic Management Activities 12/02/2024 through 12/06/2024
Anticipated Construction Activities and Traffic Management for the NHSA H6/H7 Phase 2 project for the period 12/02/2024 through 12/06/2024 is as follows:
Construction Activities
- Concrete and Internal Piping Work at the NWRP Pump Station on 13th Street between Adams and Jefferson Street. 
- Installation of Force-main and Gravity Sewer on Adams Street between 13th and 14th Street. 
- Installation of Concrete Piers and Pile caps on Adams Street between 13th and 14th Street. 
Traffic Management
- HPD Officers will be present on site to assist in traffic redirection at all construction locations. 
- No parking signs will be placed on both sides of Adams Street Between 13th and 14th Street. 
- There may be partial impacts to the sidewalks on 13th Street between Adams and Jefferson Streets within the pump station work area. 
- Adams Street between 13th Street and 14th Street will be closed to thru traffic during the day. 