Anticipated Construction Activities and Traffic Management for the NHSA H6/H7 Phase 2 project for the period 05/28/2024 through 05/31/2024 is as follows:

 

Construction Activities

  • Installing Helical Anchors on 15th Street between Adams Street and Grand Street.

    • Note: Contractor will be using an excavator to install the anchors. Contractor will be performing noise monitoring throughout the Work.

 

Traffic Management

  • 15th Street between Adams Street and Grand Street will be two lane traffic from 5/28 thru 5/31. Traffic to be shifted to North Side of 15th Street.   

  • There may be periods of time for alternating traffic, which the Officers will assist with.  

  • 2 HPD Officers will be present on site to assist in traffic redirection. One will be located at Adams, and one will be located at Grand. 

  • No parking signs will be placed on both sides of 15th Street between Adams Street and Grand Street from 5/28 thru 5/31.

  • There may be partial impacts to the sidewalks on 15th Street between Adams and Grand Streets in the Work area, however, safe passage for pedestrian traffic will be provided at all times.

Previous
Previous

North Hudson Sewerage Authority Weehawken Infrastructure Project: Two-Week Look Ahead for June 3 - June 14, 2024

Next
Next

North Hudson Sewerage Authority Weehawken Infrastructure Project Two-Week Look Ahead for May 20 - May 31, 2024