Collection System Improvements Contract 2 - Week of August 11th

Purpose of Project:
Rehabilitation of approximately 4,700 linear feet of combined sewers, manholes and service connection in the Cities of Union City and West New York.

Key Phases & Timeline

  • Sewer lining activities are expected to extend through the end of July.

Work Period & Location

  • Nighttime work 7pm to 5am: 8/12 - 3507 Park Avenue to 3343 Park Ave (union city side)

  • 8/13 - 4601 Bergenline avenue to 4705 Bergenline avenue
    *tentative* 8/14 - Hudson Avenue from 200 41st St to 139 40th St

Description of Work

  • Sewer lining

Traffic Information:

  • Road Closures: Police will be onsite to close the streets if needed.

  • Parking Restrictions: No Parking signs on both sides of the street.

  • Detours: None

  • Police presence: Yes

  • Noise/Disruptions: Sewer lining could produce some short duration noise.

We appreciate your patience and cooperation as we work to improve our infrastructure. Stay tuned for further updates!