Collection System Improvements Contract 3 - Week of August 18th, 2026
Purpose of Project:
Rehabilitation of approximately 4,700 linear feet of combined sewers, manholes and service connection in the Cities of Union City and West New York.
Key Phases & Timeline
Sewer lining activities are expected to extend through the end of August 10th - 12th.
Description of Work
sewer cleaning
Timing and Location:
Nighttime work 5pm to 5am:
8/10 & 8/12 - 57th St. between Jackson St & Bergenline Ave.
8/11 - Jackson St. from 57th St. up for 260 feet
8/13 - Jackson St. between 65th St & 62nd St.
Traffic Information:
Road Closures: Police will be onsite to close the streets if needed.
Parking Restrictions: No Parking signs on both sides of the street.
Detours: None
Police Presence: Yes; two officers
Community Impacts:
Noise/Disruptions: Sewer lining could produce some short duration noise.
We appreciate your patience and cooperation as we work to improve our infrastructure. Stay tuned for further updates!