Collection System Improvements Contract 3 - Week of August 17th, 2026

Purpose of Project:
Rehabilitation of approximately 4,700 linear feet of combined sewers, manholes and service connection in the Cities of Union City and West New York.

Key Phases & Timeline

  • Sewer lining activities are expected to extend through the end of August

Description of Work

  • Dig and Replace Sewer Main as Required in preparation for lining project

Timing and Location:

  • Monday 8/17 - 67th Street Between JFK Blvd & Jackson 10' Repair - Closest Address: 590 - 594 67th St, West New York, NJ 07093 (2x Locations)

  • Tuesday 8/18 - 67th Street Between JFK Blvd & Jackson 10' Repair - Closest Address: 584 - 586 67th St, West New York, NJ 07093

  • Tuesday 8/18 - 65th St Between Jackson & Adams 15' Repair - Closest Address: 590 65th St, West New York, NJ 07093

  • Wednesday 8/19 - 65th St Between JFK & Adams 35' Repair - Closest Address: 6402 - JFK BLVD & 65th St, West New York, NJ 07093

  • Wednesday 8/19 - Polk St Between 64th & 65th 20' Repair - Closest Address: 6404 Polk St, West New York, NJ 07093

  • Thursday 8/20 - 59th St Between Jackson & Adams 10' Repair - Closest Address: 588 59th St, West New York, NJ 07093

  • Friday 8/21 - Hudson Ave Between 61st & 62nd 10' Repair - Closest Address: 6111 - 6113 Hudson Ave, West New York, NJ 07093

  • Friday 8/21 - Hudson Ave Between 61st & 62nd 10' Repair - Closest Address: 6109 Hudson Ave, West New York, NJ 07093

Traffic Information:

  • Road Closures: Police will be onsite to close the streets if needed.

  • Parking Restrictions: No Parking signs on both sides of the street.

  • Detours: None

  • Police Presence: Yes; two officers

Community Impacts:

  • Noise/Disruptions: Sewer lining could produce some short duration noise.

We appreciate your patience and cooperation as we work to improve our infrastructure. Stay tuned for further updates!