Collection System Improvements - 3 Sewer Lining Schedule Week of August 24th, 2026
Purpose of Project:
Rehabilitation of approximately 4,700 linear feet of combined sewers, manholes and service connection in the Cities of Union City and West New York.
Key Phases & Timeline
Sewer lining activities are expected to extend through the end of August 21st - August 24th.
Description of Work
Dig and Replace Sewer Main as Required in preparation for lining project
Timing and Location:
Monday 8/24 - Hudson Ave Between 61st & 62nd - Closest Address: 6109 Hudson Ave, West New York, NJ 07093
Monday 8/24 - 56th St Between Jackson and Madison - Closest Address: 558 56th St, West New York, NJ 07093
Traffic Information:
Road Closures: Police will be onsite to close the streets if needed.
Parking Restrictions: No Parking signs on both sides of the street.
Detours: None
Police Presence: Yes; two officers
Community Impacts:
Noise/Disruptions: Dig & Replace Sewer main could produce some short duration noise.
We appreciate your patience and cooperation as we work to improve our infrastructure. Stay tuned for further updates!