Collection System Improvements Contract 2 - Week of April 28th
Purpose of Project:
Rehabilitation of approximately 4,700 linear feet of combined sewers, manholes and service connection in the Cities of Union City and West New York. 
Key Phases & Timeline
- Sewer cleaning and CCTV beginning March and continuing into April. Sewer lining beginning in May. 
Work Period & Location
- Night work 4/28, 8:30pm setup active 9:00pm thru 5am: - Berganline and 12th St 
- Park Ave and 50th St 
- Park Ave between 30th St and Cantello St 
- Hudson Ave between 40th and 41st St 
- Peter St and Hudson Ave 
 
Description of Work
- Cleaning and CCTV 
Traffic Information:
- Road Closures: Applicable roads will be closed overnight by police for the duration of active work at that location. 
- Parking Restrictions: None 
- Detours: None 
- Police presence: Yes 
- Noise/Disruptions: Sewer cleaning could produce some short duration noise. 
We appreciate your patience and cooperation as we work to improve our infrastructure. Stay tuned for further updates!