NHSA H6/H7 Hoboken Phase 3 Construction and Traffic Management Activities: December 1 - December 5, 2025

Project Overview
The goal of the project is to reduce combined sewer overflows (CSO’s) and improve the water quality of the Hudson River. As part of the project, new storm sewer lines and curb inlets will be installed which will alleviate drainage and potential flooding issues in the northern H6 and H7 drainage basins in Hoboken.

Key Phases & Timeline

  • Monday, December 1 to Friday, December 5, 2025

Construction Activities:

Pipeline Crew #1:

  • Grand Street between 14th Street and 15th Street

    • Installation of piles, pile caps, and pipe cradles

    • Installation of storm sewer pipe, manholes, and inlets

Pipeline Crew #2:

  • 14th Street between Grand Street and Clinton Street (including intersections)

    • Installation of piles, pile caps, and pipe cradles

    • Installation of storm sewer pipe, manholes, and inletss

Restoration Crews:

  • Jefferson Street and 14th Street - Jefferson St remains open

    • Sidewalk and Curb Restoration

Traffic Management:

  • Grand Street between 13th and 14th Street

    • Road open to traffic

    • Roadway changed to 2-Way traffic (north and south) to allow access to resident garages.

  • Grand Street between 14th and 15th Street

    • Road to be closed during working hours (8 am - 6 pm)

    • Roadway changed to 2-Way traffic (north and south) to allow access to resident garages.

  • 14th Street between Grand Street and Clinton Street

    • Road to be closed 24 hours, 7 days/week

    Temporary Parking Impacts: 

  • Grand Street between 13th and 14th Street

    • East side:  No parking (24/7) 

  • Grand Street between 14th and 15th Street

    • West and East side:  No parking (24/7)  

  • Clinton Street between 14th Street and 15th Street

    • Temporary no parking East side of the street, south half, from 14th St to 15th St (6am - 6 pm)

  • 13th Street between Adams Street and Grand Street

    • No parking both sides (6 am to 6 pm)

    We appreciate your patience and cooperation as we work to improve our infrastructure.