NHSA H6/H7 Hoboken Phase 3 Construction and Traffic Management Activities: Monday, March 2 - Friday, March 6, 2026

Project Overview
The goal of the project is to reduce combined sewer overflows (CSO’s) and improve the water quality of the Hudson River. As part of the project, new storm sewer lines and curb inlets will be installed which will alleviate drainage and potential flooding issues in the northern H6 and H7 drainage basins in Hoboken.

Key Phases & Timeline

  • Monday, March 2 to Friday, March 6, 2026

Construction Activities:

Pipeline Crew #1:

16th Street between Jefferson Street and Adams Street

  • Installation of storm sewer pipe, manholes, and inlets

16th Street and Adams Street Intersection

  • Installation of storm sewer pipe, manholes, and inlets

Restoration Crews: 

15th Street and Grand Street (Southeast corner)

  •   Sidewalk and Curb restoration

15th Street between Clinton Street and Willow Avenue (South Side)

  •   Sidewalk and Curb restoration

14th Street between Grand Street and Clinton

  •   Sidewalk and Curb restoration

Traffic Management:

15th Street between Grand Street and Willow Avenue

  • Road open to traffic (24 hours, 7 days/week)

Grand Street between 13th and 14th Street

  • Road open to traffic

  • Roadway changed to 2-Way traffic (north and south) to allow access to resident garages.

14th Street between Grand Street and Clinton Street

  • Road to be closed 24 hours, 7 days/week

  • Access provided to local residents and KL Masters only

16th Street between Jefferson Street and Adams Street

  • Road open to traffic

16th Street and Adams Street Intersection

  • Adams Street to be closed to traffic (8 am to 6 pm) on March 6, 2026

  • Roadway changed to 2-Way traffic (north and south) to allow access for parking

  • Traffic to be detoured to Jefferson Street or Grand Street (8 am to 6 pm)

Temporary Parking Impacts:

Grand Street between 13th and 14th Street

  • East side: No parking (24/7)

15th Street between Grand Street and Willow Avenue

  • Temporary no parking both sides of 15th Street (24/7)

13th Street between Adams Street and Grand Street

  • North side: No parking (6 am to 6 pm)

1417 to 1429 Grand Street (Odd Numbers)

  • East Side: No parking (24/7)

 16th Street between Jefferson Street and Grand Street

  • Temporary no parking both sides on 16th Street (24/7)

16th Street and Adams Street Intersection

  • Adams Street:  Temporary no parking both sides of Adams Street - 100 feet all directions of intersection on March 6, 2026

We appreciate your patience and cooperation as we work to improve our infrastructure.

Previous
Previous

NHSA H6/H7 Hoboken Phase 3 Construction and Traffic Management Activities: Monday, March 9 - Friday, March 13, 2026

Next
Next

NHSA H6/H7 Hoboken Phase 2 Construction and Traffic Management Activities: Week of March 6, 2026