NHSA H6/H7 Hoboken Phase 3 Construction and Traffic Management Activities: Monday, March 2 - Friday, March 6, 2026
Project Overview
The goal of the project is to reduce combined sewer overflows (CSO’s) and improve the water quality of the Hudson River. As part of the project, new storm sewer lines and curb inlets will be installed which will alleviate drainage and potential flooding issues in the northern H6 and H7 drainage basins in Hoboken.
Key Phases & Timeline
Monday, March 2 to Friday, March 6, 2026
Construction Activities:
Pipeline Crew #1:
16th Street between Jefferson Street and Adams Street
Installation of storm sewer pipe, manholes, and inlets
16th Street and Adams Street Intersection
Installation of storm sewer pipe, manholes, and inlets
Restoration Crews:
15th Street and Grand Street (Southeast corner)
Sidewalk and Curb restoration
15th Street between Clinton Street and Willow Avenue (South Side)
Sidewalk and Curb restoration
14th Street between Grand Street and Clinton
Sidewalk and Curb restoration
Traffic Management:
15th Street between Grand Street and Willow Avenue
Road open to traffic (24 hours, 7 days/week)
Grand Street between 13th and 14th Street
Road open to traffic
Roadway changed to 2-Way traffic (north and south) to allow access to resident garages.
14th Street between Grand Street and Clinton Street
Road to be closed 24 hours, 7 days/week
Access provided to local residents and KL Masters only
16th Street between Jefferson Street and Adams Street
Road open to traffic
16th Street and Adams Street Intersection
Adams Street to be closed to traffic (8 am to 6 pm) on March 6, 2026
Roadway changed to 2-Way traffic (north and south) to allow access for parking
Traffic to be detoured to Jefferson Street or Grand Street (8 am to 6 pm)
Temporary Parking Impacts:
Grand Street between 13th and 14th Street
East side: No parking (24/7)
15th Street between Grand Street and Willow Avenue
Temporary no parking both sides of 15th Street (24/7)
13th Street between Adams Street and Grand Street
North side: No parking (6 am to 6 pm)
1417 to 1429 Grand Street (Odd Numbers)
East Side: No parking (24/7)
16th Street between Jefferson Street and Grand Street
Temporary no parking both sides on 16th Street (24/7)
16th Street and Adams Street Intersection
Adams Street: Temporary no parking both sides of Adams Street - 100 feet all directions of intersection on March 6, 2026