NHSA H6/H7 Hoboken Phase 3 Construction and Traffic Management Activities: Monday, March 9 - Friday, March 13, 2026

Project Overview
The goal of the project is to reduce combined sewer overflows (CSO’s) and improve the water quality of the Hudson River. As part of the project, new storm sewer lines and curb inlets will be installed which will alleviate drainage and potential flooding issues in the northern H6 and H7 drainage basins in Hoboken.

Key Phases & Timeline

  • The following construction activities and traffic management are anticipated to take place from Monday, March 9 to Friday, March 13, 2026, by the NHSA - H6/H7 Phase 3 Project:

Construction Activities:

Pipeline Crew #1:

15th Street between Clinton Street and Willow Avenue (North Side)

  • Installation of piles and pile caps

  • Installation of storm sewer pipe, manholes, and inlets

16th Street and Clinton Intersection

  • Installation of piles and pile caps

  • Installation of storm sewer pipe, manholes, and inlets

16th Street and Adams Street Intersection

  • Installation of storm sewer pipe, manholes, and inlets

Pipeline Crew #2:

Clinton Street between 15th Street and 16th Street

  • Installation of piles, pile caps, and pipe cradles

  • Installation of storm sewer pipe, manholes, and inlets

Restoration Crews:

14th Street between Grand Street and Clinton

  •  Sidewalk and Curb restoration

Traffic Management:

Clinton Street between 15th Street and 16th Street

  • Road to be closed 24 hours, 7 days/week

16th Street and Clinton Street Intersection

  • Road closed to traffic (8 am to 6 pm) and road open to traffic (6 pm to 8 am)

  • Access provided to local residents and businesses

  • Traffic detoured westbound on 16th Street (8 am to 6 pm)

15th Street between Grand Street and Willow Avenue

  • Road open to traffic (24 hours, 7 days/week)

Grand Street between 13th and 14th Street

  • Road open to traffic

  • Roadway changed to 2-Way traffic (north and south) to allow access to resident garages.

14th Street between Grand Street and Clinton Street

  • Road to be closed 24 hours, 7 days/week

  • Access provided to local residents and KL Masters only

16th Street and Adams Street Intersection

  • Adams Street to be closed to traffic (8 am to 6 pm) on March 9, 2026.

  • Access provided to local traffic only 

  • Roadway changed to 2-Way traffic (north and south) on Adams Street to allow access for parking

  • Traffic to be detoured to Jefferson Street or Grand Street (8 am to 6 pm)

Temporary Parking Impacts:

Grand Street between 13th and 14th Street

  • East side: No parking (24/7)

15th Street between Grand Street and Willow Avenue

  • Temporary no parking both sides of 15th Street (24/7)

13th Street between Adams Street and Grand Street

  • North side: No parking (6 am to 6 pm)

Clinton Street between 15th Street and 16th Street

  •  Temporary no parking both sides of 15th Street (24/7)

16th Street and Adams Street Intersection

  • Adams Street: Temporary no parking both sides of Adams Street - 100 feet all directions of intersection on March 9, 2026

16th Street and Clinton Street Intersection

  • Temporary no parking  - 100 feet all directions of intersection

We appreciate your patience and cooperation as we work to improve our infrastructure.

Previous
Previous

H6/H7 CSO Long Term Control Plan Project - Phase 3 Traffic Management Activities: March 9th – April 24th, 2026

Next
Next

NHSA H6/H7 Hoboken Phase 3 Construction and Traffic Management Activities: Monday, March 2 - Friday, March 6, 2026