H6/H7 CSO Long Term Control Plan Project - Phase 3 Traffic Management Activities: March 9th – April 24th, 2026

Project Overview
The goal of the project is to reduce combined sewer overflows (CSO’s) and improve the water quality of the Hudson River. As part of the project, new storm sewer lines and curb inlets will be installed which will alleviate drainage and potential flooding issues in the northern H6 and H7 drainage basins in Hoboken.

Key Phases & Timeline

  • On or about March 9th, 2026 to April 24th, 2026

  • Work hours – 8:00am to 6:00pm

Locations Impacted by Construction:

  • 13th Street between Grand Street and Willow Avenue

Construction Activities:

  • Installation of sewer pipe, inlets, and manholes

  • Road closure (24 hours, 7 days/week), however residences will be granted access. Detour signage will be in place.

  • HPD Officers will be present on site to assist in traffic redirection

  • No parking (24 hours, 7 days/week) along 13th Street

We appreciate your patience and cooperation as we work to improve our infrastructure.

Previous
Previous

NHSA H6/H7 Hoboken Phase 2 Construction and Traffic Management Activities: Week of March 9, 2026

Next
Next

NHSA H6/H7 Hoboken Phase 3 Construction and Traffic Management Activities: Monday, March 9 - Friday, March 13, 2026