NHSA H6/H7 Hoboken Phase 3 Construction and Traffic Management Activities: Monday, May 11 to Saturday, May 16, 2026

Project Overview
The goal of the project is to reduce combined sewer overflows (CSO’s) and improve the water quality of the Hudson River. As part of the project, new storm sewer lines and curb inlets will be installed which will alleviate drainage and potential flooding issues in the northern H6 and H7 drainage basins in Hoboken.

Key Phases & Timeline

  • The following construction activities and traffic management are anticipated to take place from Monday, May 11, to Saturday, May 16, 2026 by the NHSA - H6/H7 Phase 3 Project:

Construction Activities:

Construction Activities:

13th Street between Grand Street and Clinton Street

  • Installation of sanitary sewer and manhole

16th Street and Clinton Street intersection

  • Repair of outfall pipe

Restoration Activities:

14th Street between Grand Street and Clinton

  • Installation of the Cobblestone roadway

Grand Street between 13th Street and 15th Street

  • Sidewalk and Curb restoration

15th Street and Clinton Street Intersection

  • Sidewalk and curb restoration

Traffic Management:

14th Street between Grand Street and Clinton Street

  • Road to be closed 24 hours, 7 days/week

  • Access provided to local residents and KL Masters only

13th Street between Adams Street and Grand Street

  • Road closed to thru traffic, local traffic only (8 am to 6 pm)

  • Access to 13th Street parking garages and local residents will be accessed from Adams Street

13th Street between Grand Street and Clinton Street

  • Road closed to thru traffic, local traffic only (8 am to 6 pm)

  • Access to 13th Street parking garages and local residents will be accessed from Grand Street

13th Street between Clinton Street and Willow Avenue

  • Roadway changed to 2-Way traffic (east and west) on 13th Street between Clinton Street and Willow Avenue

  • Road open to traffic

Temporary Parking Impacts:

Grand Street between 13th and 14th Street

  • East side: Temporary no parking (24/7)

  • West side: Temporary no parking (24/7)

13th Street between Adams Street and Willow Avenue

  • Temporary no parking on both sides of 13th Street (24/7)

Grand Street between 14th Street and 15th Street

  • Temporary no parking east side of Grand Street no. 1418 to 1427 (6 am to 6 pm)

 

We appreciate your patience and cooperation as we work to improve our infrastructure.