Project Overview
The goal of the project is to reduce combined sewer overflows (CSO’s) and improve the water quality of the Hudson River. As part of the project, new storm sewer lines and curb inlets will be installed which will alleviate drainage and potential flooding issues in the northern H6 and H7 drainage basins in Hoboken.
Key Phases & Timeline
The following construction activities and traffic management are anticipated to take place from Monday, May 18, to Saturday, May 23, 2026 by the NHSA - H6/H7 Phase 3 Project:
Construction Activities:
Construction Activities:
13th Street between Grand Street and Willow Avenue
Installation of sanitary sewer and manhole
Restoration Activities:
Grand Street between 13th Street and 15th Street
Sidewalk and curb restoration
14th Street between Grand Street and Clinton
Installation of cobblestone roadway
15th Street and Clinton Street Intersection
Sidewalk and curb restoration
Traffic Management:
13th Street between Adams Street and Willow Avenue
Road closed to thru traffic, local traffic only (8 am to 6 pm)
Access to 13th Street parking garages and local residents will be accessed from Adams Street or Grand Street
13th Street and Clinton Street Intersection
Road closed 24 hours, 7 days/week
Access to 13th Street parking garages and local residents will be accessed from Grand Street
13th Street between Clinton Street and Willow Avenue
Road closed to thru traffic, open to local traffic only (8am to 6pm)
14th Street between Grand Street and Clinton Street
Road closed 24 hours, 7 days/week
Access provided to local residents and KL Masters only
Temporary Parking Impacts:
13th Street between Adams Street and Willow Avenue
Temporary no parking on both sides of 13th Street (24/7)
Grand Street between 13th and 14th Street
East side: Temporary no parking (24/7)
West side: Temporary no parking (24/7)
Grand Street between 14th Street and 15th Street
Temporary no parking east side of Grand Street #1418 - 1427 (6 am to 6 pm)
We appreciate your patience and cooperation as we work to improve our infrastructure.