Madison Street Infrastructure Improvements: Construction and Traffic Management Activities Week of October 20th
Madison Street Infrastructure Improvements
The Madison Street Area Infrastructure Improvements project has been undertaken to mitigate localized flooding from rain events. To accomplish this, the project scope includes replacing existing inlets and sewer lines as well as elevating roadways, curbs, and sidewalks within the area. Ultimately, these improvements will alleviate the primary concerns by conveying the stormwater into the sewer system.
The following work and traffic management activities are anticipated for Monday, Oct 20th through Friday, Oct 24th between the hours of 8 a.m. and 4 p.m.:
Work Activities:
9th Street between Madison Street and Monroe Street
Finish installation of brick paver sidewalk.
Madison Street Between 9th and 10th Street.
Demo existing sidewalk on the east side of Madison Street
Install 901 and 915 Madison Street Driveway.
Install concrete curbs on the east side of Madison Street.
Install concrete sidewalk on the east side of Madison Street.
Reset existing brick pavers on the east side of Madison Street.
Madison Street and 11th Street Intersection. (Subject to coordination with Hoboken Engineering)
Install 16” Water main pipe.
Install 16” Water main tee.
Install 8” Water main pipe .
Install Flexible Expansion Joints.
Traffic Management:
9th Street between Madison Street and Monroe Street
One Lane traffic will be open. (24/7)
NO PARKING is allowed on both sides.
9th Street and Madison Street intersection
No Impacts, One lane will be open as of now – Depending on water main work installation pending answers.
Madison Street between 9th Street and 10th Street
One lane traffic will be open.
Road to be closed periodically during the material deliveries from 9AM – 4PM.
10th Street between Jefferson Street and Madison Street
No Impact to existing traffic flow. – Depends on the water main installation pending answers.
Madison Street / 11th Street Intersection
No Impact to existing traffic flow. – Depending on water main work installation pending answers.
Madison Street between 11th Street and 12th Street
No Impact to existing traffic flow. – Depending on water main work installation pending answers.
11th Street between Monroe and Madison Street
No Impact to Existing Traffic flow. – Depending on water main work installation pending answers.
Temporary Parking Impacts:
9th Street between Madison and Monroe Street
No parking on either side of the street (24/7)
9th Street between Madison and Jefferson Street
No Parking on the North Side of 9th Street. (24/7)
Madison Street between 9th and 10th Street
No parking on either side of the street (24/7)
Madison Street between 10th and 11th Street
100% parking will be available on the east side (24/7)
50% parking will be available on the west side (24/7)
10th Street between Madison and Jefferson Street
No Impact.
11th St between Madison and Monroe Street.
No Impact.
HPD will be on-site to assist with traffic management during construction.