NHSA H6/H7 Hoboken Phase 3 Construction and Traffic Management Activities: October 20th – October 24th, 2025
Project Overview
The goal of the project is to reduce combined sewer overflows (CSO’s) and improve the water quality of the Hudson River. As part of the project, new storm sewer lines and curb inlets will be installed which will alleviate drainage and potential flooding issues in the northern H6 and H7 drainage basins in Hoboken.
Key Phases & Timeline
Monday, October 20 to Friday, October 24, 2025
Construction Activities:
Pipeline Crew #1:
Grand Street between 14th Street and 15th Street
Installation of piles, pile caps, and pipe cradles
Installation of storm sewer pipe, manholes, and inlets
Pipeline Crew #2:
14th Street between Grand Street and Clinton Street (including intersections)
Relocation of electrical services and 8-inch water main
Installation of piles, pile caps, and pipe cradles
Installation of storm sewer pipe, manholes, and inlets
Restoration Crew:
13th Street and Adams Street (northeast corner – 13th St remains open)
Sidewalk and Curb restoration
Madison Street between 13th and 14th Street - Madison St remains open
Sidewalk Restoration
Traffic Management:
Grand Street between 13th and 14th Street
Road to be closed during working hours (8 am - 6 pm)
Roadway changed to 2-Way traffic (north and south) to allow access to resident garages.
14th Street between Grand Street and Clinton Street (including intersections)
Road to be closed 24 hours, 7 days/week
Temporary Parking Impacts:
Grand Street between 13th and 15th Street
East side: No parking (24/7)
West side: No parking (6 am to 6 pm)
Clinton Street between 14th Street and 15th Street
Temporary no parking east side of the street, south half, from 14th St to 15th St (6am - 6 pm)
We appreciate your patience and cooperation as we work to improve our infrastructure.