NHSA H6/H7 Hoboken Phase 2 Construction and Traffic Management Activities: Week of October 13th - October 17th

Project Overview
We’re continuing Phase 2 of the H6/H7 Project to enhance infrastructure reliability and improve stormwater management in Hoboken. This work will support long-term system efficiency and reduce maintenance needs.

Key Phases & Timeline

  • Week of October 13th - 17th, 2025

  • Work Locations:

    • 13th Street between Adams and Jefferson Streets

    • Adams Street between 14th and 15th Streets

Construction Activities

  • Electrical installation and plumbing installation for the pumps at the NWRP Pump Station on 13th Street between Adams and Jefferson Streets.

  • Grating and Stair installation and anchorage.

  • Installation of Sound Proofing Spray

  • Load bank installation on roof

Traffic Management

  • No parking on 13th Street between Adams and Jefferson Streets between the hours of 6AM to 6PM.

We appreciate your patience and cooperation as we work to improve our infrastructure.