Madison Street Infrastructure Improvements: Construction and Traffic Management Activities May 5th - May 9th

Madison Street Infrastructure Improvements

The Madison Street Area Infrastructure Improvements project will help mitigate localized flooding from rain events. The project scope includes replacing existing inlets, sewers, and water lines as well as elevating roadways, curbs, and sidewalks within the area. These improvements will alleviate the primary concerns by conveying stormwater into the sewer system.  

Work on the Madison Street Area Infrastructure Improvements will require parking restrictions, partial road closures, and 24-hour closure of Madison. Area residents will be kept apprised of the work and impacts on their quality of life.  

The following work and traffic management activities are anticipated for Monday, May 5th through Friday, May 9th between the hours of 8 a.m. and 4 p.m.:

Work Activities:

  • Madison St between 10th and 11th Street 

    • Maintain Sewer Bypass b/w 10th St and 11th St.

    • Backfilling for the sidewalk installation.  

    • Demo existing sidewalk at 1000 Jefferson Side.

    • Pour Sidewalk at 1000 Jefferson Side.  

    • Pour sidewalk in front of 1000 Jefferson coffee.

  •  Madison St between 9th and 10th Street 

    • Demo the existing road between 9th and 10th St.

    • Start Installing Helical Piles between 9th and 10th St.

    • Test pit for the existing conditions for the electrical utilities. 

Traffic Management:

  • Madison St full closure between 10th and 11th Street.

  • No-Parking on Madison St between 10th and 11th Street.

  • HPD will be on-site to assist with traffic management during construction.

Previous
Previous

NHSA H6/H7 Hoboken Phase 2 Construction and Traffic Management Activities: May 5th – May 9th, 2025

Next
Next

NHSA H6/H7 Hoboken Phase 3 Construction and Traffic Management Activities: May 5th – May 9th, 2025