Madison Street Infrastructure Improvements: Construction and Traffic Management Activities May 12th - May 16th
Madison Street Infrastructure Improvements
The Madison Street Area Infrastructure Improvements project will help mitigate localized flooding from rain events. The project scope includes replacing existing inlets, sewers, and water lines as well as elevating roadways, curbs, and sidewalks within the area. These improvements will alleviate the primary concerns by conveying stormwater into the sewer system.
Work on the Madison Street Area Infrastructure Improvements will require parking restrictions, partial road closures, and 24-hour closure of Madison. Area residents will be kept apprised of the work and impacts on their quality of life.
The following work and traffic management activities are anticipated for Monday, May 12th through Friday, May 16th between the hours of 8 a.m. and 4 p.m.:
Work Activities:
Madison St between 10th and 11th Street
Maintain Sewer Bypass b/w 10th St and 11th St.
Backfilling for the sidewalk installation on the east side of Madison Street b/w 10th & 11th St.
Install the ADA Ramp in front of Jefferson’s Coffee.
Install the ADA ramp in front of 1000 Jefferson entrance on Madison St.
Install brick pavers at Madison St. b/w 10th & 11th St.
Madison St between 9th and 10th Street
Start Installing Helical Piles b/w 9th and 10th St.
Test pit for the existing conditions for the electrical utilities.
Traffic Management:
Madison St full closure between 10th and 11th Street.
No-Parking on Madison St between 10th and 11th Street.
HPD will be on-site to assist with traffic management during construction.