Madison Street Infrastructure Improvements: Construction and Traffic Management Activities June 16th - June 20th

Madison Street Infrastructure Improvements

The Madison Street Area Infrastructure Improvements project will help mitigate localized flooding from rain events. The project scope includes replacing existing inlets, sewers, and water lines as well as elevating roadways, curbs, and sidewalks within the area. These improvements will alleviate the primary concerns by conveying stormwater into the sewer system.  

Work on the Madison Street Area Infrastructure Improvements will require parking restrictions, partial road closures, and 24-hour closure of Madison. Area residents will be kept apprised of the work and impacts on their quality of life.  

The following work and traffic management activities are anticipated for Monday, June 16th through Friday, June 20th between the hours of 8 a.m. and 4 p.m.:

Work Activities:

  • Madison Street / 10th Street Intersection.

    • Install Helical Piles, Pile Caps, New Sewer, and New Water.

    • Install the 16” Gate Valve.

    • Install the tee for future 10th Street tie-in.

    • Backfill and Pave asphalt. 

  • Madison Street between 9th and 10th Street.

    • Install Helical Piles, Manhole, Precast structures, Maintain Sewer Bypass.

    • Garage access will be maintained for 915 and 901 Madison Street.

Traffic Management:

  • Madison Street between 10th and 11th Street will be closed.

  • Madison Street between 9th and 10th Street will be closed.

  • Madison Street and 10th Street intersection will be closed.

  • HPD will be on-site to assist with traffic management during construction.