Madison Street Infrastructure Improvements: Construction and Traffic Management Activities July 14th - July 18th
Madison Street Infrastructure Improvements
The Madison Street Area Infrastructure Improvements project will help mitigate localized flooding from rain events. The project scope includes replacing existing inlets, sewers, and water lines as well as elevating roadways, curbs, and sidewalks within the area. These improvements will alleviate the primary concerns by conveying stormwater into the sewer system.
Work on the Madison Street Area Infrastructure Improvements will require parking restrictions, partial road closures, and 24-hour closure of Madison. Area residents will be kept apprised of the work and impacts on their quality of life.
The following work and traffic management activities are anticipated for Monday, July 14th through Friday, July 18th between the hours of 8 a.m. and 4 p.m.:
Work Activities:
Madison Street between 9th and 10th Street
Install Helical Piles.
Maintain Sewer Bypass.
Demo existing sewer.
Perform test pits for the lateral connections.
Install 36” sewer and 16” water main.
Traffic Management:
Parking spaces will be available on the East side of Madison Street between 10th and 11th.
No-Parking on Madison Street between 10th and 11th Street on the West Side.
Madison Street between 9th and 10th Street will be closed.
HPD will be on-site to assist with traffic management during construction.
Access will be maintained for 915 Madison Street from 10th Street.
No access for the 901 Madison Street from Madison Street.