NHSA H6/H7 Hoboken Phase 2 Construction and Traffic Management Activities: April 7th – April 11th, 2025
Project Overview
We’re continuing Phase 2 of the H6/H7 Project to enhance infrastructure reliability and improve stormwater management in Hoboken. This work will support long-term system efficiency and reduce maintenance needs.
Key Phases & Timeline
- Week of April 7th – April 11th, 2025 
- Work Locations: - 13th Street between Adams and Jefferson Streets 
- Adams Street between 13th and 15th Streets 
 
Construction Activities
- Working on louvers, pipe rails and painting for the pumps at the NWRP Pump Station on 13th Street between Adams and Jefferson Streets 
- Installation of bollards, concrete curb, and sidewalk work under viaduct at the intersection of 14th and Adams Street 
- Installation of curbs and curb walls on 15th and Adams Streets 
Traffic Management
- Adams Street between 13th and 15th Streets will be closed to thru traffic for curb and sidewalk work, but open to thru traffic at night. 
- 15th Street will have traffic going East and Westbound from Adams to Willow. Flow will resume as normal. 
- HPD officers will be present at all intersections. 
- 24/7 no parking signs will be in place on both sides of Adams Street between 13th and 15th Streets. 
We appreciate your patience and cooperation as we work to improve our infrastructure.