NHSA H6/H7 Hoboken Phase 2 Construction and Traffic Management Activities: Week of September 1 - September 5

Project Overview
We’re continuing Phase 2 of the H6/H7 Project to enhance infrastructure reliability and improve stormwater management in Hoboken. This work will support long-term system efficiency and reduce maintenance needs.

Key Phases & Timeline

  • Week of September 1st - 5th, 2025

  • Work Locations:

    • 13th Street between Adams and Jefferson Streets

    • Adams Street between 14th and 15th Streets

Construction Activities

  • Electrical installation and plumbing installation for the pumps at the NWRP Pump Station on 13th Street between Adams and Jefferson Streets

  • Temporary striping on 15th Street between Adams Street and Willow Avenue

Traffic Management

  • 09/01/2025 – Labor Day – No Work for Contractor

  • 15th Street will have traffic detoured to 13th Street on the day we are temporary striping.

  • HPD will be on site to manage traffic control during striping operations.

We appreciate your patience and cooperation as we work to improve our infrastructure.

Previous
Previous

NHSA H6/H7 Hoboken Phase 3 Construction and Traffic Management Activities: September 1st – September 5th, 2025

Next
Next

Madison Street Infrastructure Improvements: Construction and Traffic Management Activities Week of September 2, 2025