NHSA H6/H7 Hoboken Phase 3 Construction and Traffic Management Activities: June 30th – July 4th, 2025
Project Overview
The goal of the project is to reduce combined sewer overflows (CSO’s) and improve the water quality of the Hudson River. As part of the project, new storm sewer lines and curb inlets will be installed which will alleviate drainage and potential flooding issues in the northern H6 and H7 drainage basins in Hoboken.
Key Phases & Timeline
June 30th to July 4th, 2025
Holiday: July 4th: No Scheduled Work
Work hours – 8:00am to 6:00pm
Work Locations:
13th Street between Adams Street and Clinton Street
Grand Street between 13th Street and 14th Street
Description of work:
16th Street and Jefferson Street Intersection
Installation of new sewer piping
Jefferson Street
Sidewalk and Curb restoration on Jefferson at 14th
Installation of catch basins along Jefferson Street between 15th Street and 16th Street
Adams Street between 15th Street and 16th Street
Installation of piles, pile caps, concrete cradles
Installation of 18" Storm pipe
Installation of manholes
Excavate for PSE&G to relocate gas piping
Madison Street between 13th and 14th
Sidewalk and Curb restoration
15th Street between Adams Street and Grand Street
Installation of piles, pile caps, concrete cradles
Installation of 24" Storm pipe
Installation of manholes
13th Street between Adams Street and Grand Street
Installation of piles, pile caps, and concrete cradles
Installation of 48" Storm pipe
Installation of manholes
Traffic Management:
15th Street between Jefferson Street and Grand Street
No parking (24 hours, 7 days/week) signs will be placed on both sides
Roadway closed to Eastbound traffic 8 a.m. to 6 p.m.
Eastbound traffic detoured to Jefferson Street and 16th Street
Westbound traffic of 15th is open during working hours
Academy Bus Services can access work area to enter/exit their parking lots.
Buses must use Jefferson Street and 16th Street to exit all parking lots to proceed to Willow Street as 15th Street eastbound is closed to traffic.
13th Street between Jefferson and Madison
No parking (24 hours, 7 days/week) signs will be placed on both sides of the Street.
Jefferson Street between 13th Street and 16th Street
No parking (24 hours, 7 days/week) both sides of the street
Adams Street between 15th Street and 16th Street
No parking (24 hours, 7 days/week) both sides of the streets
Road closed during working hours and road open during non-working hours
Madison and Jefferson Street between 14th and 15th Street
No parking (24 hours, 7 days/week) both sides of the streets
Academy Bus Service re-configured entrance/exit routing
Grand Street between 15th and 16th Street
No parking (24 hours, 7 days/week) on both sides of the street.
16th Street between Jefferson Street and Adams Street
Section of roadway is open to two way traffic (east and west)
No Parking (24 hours, 7 days per week) both sides of the street
16th Street between Adams Street and Grand Street
No Parking (24 hours, 7 days per week) both sides of the street
Roadway open to traffic
13th Street between Adams Street and Grand Street
No parking (24 hours, 7 days/week) signs will be placed on both sides of 13th Street between Adams Street and Clinton Street
Road to be closed 24 hours, 7 days/week however residents will be allowed access in from Grand St to 1300 Grant St garage. 1200 Grand St garage to be accessed via 12th Street.
Traffic detour: Grand St to 11 St to Adams Street
We appreciate your patience and cooperation as we work to improve our infrastructure.