NHSA H6/H7 Hoboken Phase 3 Construction and Traffic Management Activities: July 7th – July 10th, 2025

Project Overview
The goal of the project is to reduce combined sewer overflows (CSO’s) and improve the water quality of the Hudson River. As part of the project, new storm sewer lines and curb inlets will be installed which will alleviate drainage and potential flooding issues in the northern H6 and H7 drainage basins in Hoboken.

Key Phases & Timeline

  • July 7th to July 10th, 2025

  • Holiday: July 4th:  No Scheduled Work

  • Work hours – 8:00am to 6:00pm

Description of work:

Jefferson Street

  • Sidewalk and Curb restoration on Jefferson at 14th

Adams Street between 15th Street and 16th Street

  • Installation of piles, pile caps, concrete cradles

  • Installation of 18" Storm pipe

  • Installation of manholes

Madison Street between 13th and 14th

  • Sidewalk and Curb restoration

15th Street between Adams Street and Grand Street

  • Installation of piles, pile caps, concrete cradles

  • Installation of 24" Storm pipe

  • Installation of manholes

13th Street between Adams Street and Grand Street

  • Installation of piles, pile caps, and concrete cradles

  • Installation of 48" Storm pipe

  • Installation of manholes

Traffic Management:

  • 15th Street between Jefferson Street and Grand Street

    • No parking (24 hours, 7 days/week) signs will be placed on both sides  

    • Roadway closed to Eastbound traffic 8 a.m. to 6 p.m.

    • Eastbound traffic detoured to Jefferson Street and 16th Street

    • Westbound traffic of 15th is open during working hours

    • Academy Bus Services can access work area to enter/exit their parking lots.  

    • Buses must use Jefferson Street and 16th Street to exit all parking lots to proceed to Willow Street as 15th Street eastbound is closed to traffic.

    13th Street between Jefferson and Madison

    • No parking (24 hours, 7 days/week) signs will be placed on both sides of the Street.

    Jefferson Street between 13th Street and 16th Street  

    • No parking (24 hours, 7 days/week) both sides of the street  

    Adams Street between 15th Street and 16th Street  

    • No parking (24 hours, 7 days/week) both sides of the streets  

    • Road closed during working hours and road open during non-working hours  

    Madison and Jefferson Street between 14th and 15th Street  

    • No parking (24 hours, 7 days/week) both sides of the streets  

    • Academy Bus Service re-configured entrance/exit routing

    Grand Street between 15th and 16th Street

    • No parking (24 hours, 7 days/week) on both sides of the street.

    • Road used as staging area  

    16th Street between Jefferson Street and Adams Street  

    • Section of roadway is open to two way traffic (east and west)

    • No Parking (24 hours, 7 days per week) both sides of the street

    16th Street between Adams Street and Grand Street

    • No Parking (24 hours, 7 days per week) both sides of the street

    13th Street between Adams Street and Grand Street

    • No parking (24 hours, 7 days/week) signs will be placed on both sides of 13th Street between Adams Street and Clinton Street

    • Road to be closed 24 hours, 7 days/week however residents will be allowed access in from Grand St to 1300 Grant St garage. 1200 Grand St garage to be accessed via 12th Street.

    • Traffic detour: Grand St to 11 St to Adams Street

We appreciate your patience and cooperation as we work to improve our infrastructure.

Previous
Previous

Madison Street Infrastructure Improvements: Construction and Traffic Management Activities July 7th - July 11th

Next
Next

NHSA H6/H7 Hoboken Phase 3 Construction and Traffic Management Activities: June 30th – July 4th, 2025