H6/H7 CSO Long Term Control Plan Project - Phase 3 Traffic Management Activities: August 4th – August 8th, 2025
Project Overview
The goal of the project is to reduce combined sewer overflows (CSO’s) and improve the water quality of the Hudson River. As part of the project, new storm sewer lines and curb inlets will be installed which will alleviate drainage and potential flooding issues in the northern H6 and H7 drainage basins in Hoboken.
Key Phases & Timeline
Monday, August 4th to Friday, August 15th, 2025
Work hours – 8:00am to 6:00pm
Locations Impacted by Construction:
Clinton Street between 13th Street and 14th Street
Construction Activities:
Installation of sewer pipe, inlets, and manholes
Road closure (8am to 6pm), however residences will be granted
access.
HPD Officers will be present on site to assist in traffic
redirection
No parking (24 hours, 7 days/week)
We appreciate your patience and cooperation as we work to improve our infrastructure.