NHSA H6/H7 Hoboken Phase 3 Construction and Traffic Management Activities: August 4th – August 8th, 2025

Project Overview
The goal of the project is to reduce combined sewer overflows (CSO’s) and improve the water quality of the Hudson River. As part of the project, new storm sewer lines and curb inlets will be installed which will alleviate drainage and potential flooding issues in the northern H6 and H7 drainage basins in Hoboken.

Key Phases & Timeline

  • Monday, August 4th to Friday, August 8th, 2025

  • Work hours – 8:00am to 6:00pm

Construction Activities:

  • Jefferson Street

    • Sidewalk and Curb restoration on Jefferson at 14th

  • Madison Street between 13th and 14th

    • Sidewalk and Curb restoration

  • Adams Street between 15th Street and 16th Street

    • Installation of catch basin inlets and associated piping

  • Grand Street between 15th Street and 16th Street

    • Installation of piles and pile caps

    • Installation of 18" Storm pipe

    • Installation of manholes

  • Grand Street between 13th Street and 14th Street

    • Installation of piles, pile caps, and pipe cradles

    • Installation of 36" Storm pipe

    • Installation of manholes

  • Clinton Street between 13th Street and 14th Street

    • Installation of piles, pile caps, and pipe cradles

    • Installation of 18" Storm pipe

    • Installation of manholes and catch basin inlets

Traffic Impacts/Management:

  • 15th Street between Adams Street and Grand Street

    • No parking (24 hours, 7 days/week) signs will be placed on both sides  

    • Roadway open to all traffic

    • Academy Bus Services can access work area to enter/exit their parking lots.  

  • 13th Street between Jefferson and Madison

    • No parking (24 hours, 7 days/week) signs will be placed on both sides of the Street.

    • Jefferson Street between 13th Street and 14th Street  

    • No parking (24 hours, 7 days/week) both sides of the street  

  • Madison and Jefferson Street between 14th and 15th Street  

    • No parking (24 hours, 7 days/week) both sides of the streets  

    • Academy Bus Service re-configured entrance/exit routing

  • Grand Street between 15th and 16th Street

    • No parking (24 hours, 7 days/week) on both sides of the street.

    • Road to be closed 24 hours, 7 days/week

    • Road used as staging area  

  • Grand Street between 13th and 14th Street

    • No parking (24 hours, 7 days/week) on both sides of the street.

    • Road to be closed during working hours (8 am to 6 pm) and road open during non-working hours.

    • Grand Street: Roadway changed to 2-Way traffic (north and south) to allow access to resident garages/driveways.

    • Access to resident garages will be available during working hours and non-working hours.

  • 16th Street between Jefferson Street and Adams Street  

    • Section of roadway is open to two-way traffic (east and west)

    • No Parking (24 hours, 7 days per week) both sides of the street

  • 16th Street between Adams Street and Grand Street

    • No Parking (24 hours, 7 days per week) both sides of the street

  • 13th Street between Adams Street and Grand Street

    • No parking (24 hours, 7 days/week) signs will be placed on both sides of 13th Street between Adams Street and Clinton St

    • Roadway open to all traffic

  • Clinton Street between 13th Street and 14th Street

    • No parking (24 hours, 7 days/week) signs will be placed on both sides of Clinton Street between 13th Street and 14th St

    • Road to be closed during working hours (8 am to 6 pm) and road open during non-working hours.

    • Access to resident garages/driveways will be available during working hours and non-working hours.

We appreciate your patience and cooperation as we work to improve our infrastructure.

Previous
Previous

H6/H7 CSO Long Term Control Plan Project - Phase 3 Traffic Management Activities: August 4th – August 8th, 2025

Next
Next

Collection System Improvements Contract 4 - Week of July 28th