Collection System Improvements Contract 4 - Week of July 28th

Purpose of Project:
Rehabilitation of approximately 4,700 linear feet of combined sewers, manholes and service connection in the Cities of Union City and West New York.

Key Phases & Timeline

  • Late February, contractor mobilize to Park Avenue Siphon Chamber

Work Period & Location

  • Daytime and Nighttime work, 7/28 thru 8/1:

  • 7/28 – Daytime 7am to 2pm – CCTV of sanitary main on 52nd & 54thSt, West New York, cutting protruding laterals on Adams St, West New York.

  • Nighttime 9pm to 4am – lining of sanitary main on 52nd St, West New York

  • 7/29 - Nighttime 9pm to 4am – lining of sanitary main on 54th St, West New York

  • 7/30 - Nighttime 9pm to 4am – lining of sanitary main on 52nd St, West New York

  • 7/31 - Nighttime 9pm to 4am – lining of sanitary main on 52nd St, West New York

Description of Work

  • Preparing sanitary main for lining

Traffic Information:

  • Road Closures: Police will be onsite to close the streets if needed.

  • Parking Restrictions: None

  • Detours: None

  • Police presence: Yes

  • Noise/Disruptions: Sewer lining could produce some short duration noise.

We appreciate your patience and cooperation as we work to improve our infrastructure. Stay tuned for further updates!