H6/H7 CSO Long Term Control Plan Project - Phase 3 Traffic Management Activities: June 22nd – June 26th, 2026

Project Overview
The goal of the project is to reduce combined sewer overflows (CSO’s) and improve the water quality of the Hudson River. As part of the project, new storm sewer lines and curb inlets will be installed which will alleviate drainage and potential flooding issues in the northern H6 and H7 drainage basins in Hoboken.

Key Phases & Timeline

  • Work hours – 8:00am to 6:00pm

work Impact:

  • No parking will be in effect during milling, paving, and striping activities

  • Roads will be closed during milling and paving activities

Construction Activities:

Paving and Striping Activities for the project will begin and the anticipated schedule which is subject to change based on weather and progress is as follows. Streets will be closed to traffic during this work. There will also be Temporary No Parking to accommodate this work.

  • 6/22 Monday: NO ROADWAY WORK – WORLD CUP GAME AT METLIFE STADIUM

  • 6/23 Tuesday: 8 am - 6 pm: Clinton St (14th St to 15th St ) and Jefferson St (13th St to 15th St)

  • 6/24 Wednesday: 8 am - 6 pm: Clinton St (14th St to 15th St ) and Jefferson St (13th St to 15th St)

  • 6/25 Thursday: NO ROADWAY WORK – WORLD CUP GAME AT METLIFE STADIUM

  • 6/19 Friday: 8 am - 6 pm: Clinton St (13th to 14th), and Madison St (13th St to 15th St)

Note that there will be periodic curb and sidewalk restoration throughout the area however, roadways will remain open during this work.