NHSA - Port Imperial Pump Station No. 3 Rehabilitation

Week-by-Week Overview of Project Phases and Timelines

Week 1:  Thursday, 1-18 and Friday 1-19, the Contractor will mobilize to the site, which include the delivery of equipment.

 

Week 2:  1-22 to 1-26 the Contractor will begin setting up the by-pass pumps.  On Tuesday 1-23 and Wednesday, 1-24, the Contractor will be excavating in Port Imperial Boulevard to install the by-pass piping.  The roadway will be reopened at the end of each shift.

 

Week 3:  1- 29 to 2-1 the Contractor will put the pumping station on by-pass and work around the clock to complete the work inside of the pumping station.  The work will not involve excavation but the Contractor will have light tower set-up.  The work is scheduled to take 5-days. 

 

Week 4:  2-4 to 2-8 the Contractor will demobilize and remove materials and equipment.  They will also have to work within Port Imperial Boulevard.

Previous
Previous

North Hudson Sewerage Authority Weehawken Infrastructure Project Two Week Look Ahead For 1/22 - 2/02/2024

Next
Next

NHSA H6/H7 Phase 2 - Construction And Traffic Management Activities 01/08/2024 - 01/12/2024