Collection System Improvements Contract 4 - Week of October 27th

Purpose of Project:
Rehabilitation of approximately 4,700 linear feet of combined sewers, manholes and service connection in the Cities of Union City and West New York.

Key Phases & Timeline

  • Sewer lining activities are expected to extend through mid-December.

Work Period & Location

  • Monday - 10/27 

    Daytime - Preparing sanitary mains for lining in West New York

    Nighttime (8pm start) – Line sanitary mains on Adams St and 67thSt, West New York

  • Tuesday - 10/28

    Daytime – Preparing sanitary mains for lining in West New York

    Nighttime (8pm start) – Line sanitary mains on 54th St, West New York

  • Wednesday - 10/29

    Daytime – Preparing sanitary mains for lining in West New York

    Nighttime (8pm start) – Line sanitary mains on 58th St and JFK Blvd E, West New York

  • Thursday - 10/30

    Daytime – Preparing sanitary mains for lining in West New York

    Nighttime (8pm start) – Line sanitary mains on 61st St and Palisades Ave, West New York

  • Friday - 10/31

    Daytime – Preparing sanitary mains for lining in West New York

Description of Work

  • Preparing sanitary main for lining, lining of sanitary sewer mains

Traffic Information:

  • Road Closures: Police will be onsite to close the streets if needed.

  • Parking Restrictions: No Parking signs on both sides of the street as needed.

  • Detours: None

  • Police presence: Yes

  • Noise/Disruptions: Sewer lining could produce some short duration noise.

We appreciate your patience and cooperation as we work to improve our infrastructure. Stay tuned for further updates!