Collection System Improvements Contract 4 - Week of October 27th
Purpose of Project:
Rehabilitation of approximately 4,700 linear feet of combined sewers, manholes and service connection in the Cities of Union City and West New York.
Key Phases & Timeline
Sewer lining activities are expected to extend through mid-December.
Work Period & Location
Monday - 10/27
Daytime - Preparing sanitary mains for lining in West New York
Nighttime (8pm start) – Line sanitary mains on Adams St and 67thSt, West New York
Tuesday - 10/28
Daytime – Preparing sanitary mains for lining in West New York
Nighttime (8pm start) – Line sanitary mains on 54th St, West New York
Wednesday - 10/29
Daytime – Preparing sanitary mains for lining in West New York
Nighttime (8pm start) – Line sanitary mains on 58th St and JFK Blvd E, West New York
Thursday - 10/30
Daytime – Preparing sanitary mains for lining in West New York
Nighttime (8pm start) – Line sanitary mains on 61st St and Palisades Ave, West New York
Friday - 10/31
Daytime – Preparing sanitary mains for lining in West New York
Description of Work
Preparing sanitary main for lining, lining of sanitary sewer mains
Traffic Information:
Road Closures: Police will be onsite to close the streets if needed.
Parking Restrictions: No Parking signs on both sides of the street as needed.
Detours: None
Police presence: Yes
Noise/Disruptions: Sewer lining could produce some short duration noise.
We appreciate your patience and cooperation as we work to improve our infrastructure. Stay tuned for further updates!