Collection System Improvements Contract 4 - Week of July 25th
Purpose of Project:
Rehabilitation of approximately 4,700 linear feet of combined sewers, manholes and service connection in the Cities of Union City and West New York.
Key Phases & Timeline
Late February, contractor mobilize to Park Avenue Siphon Chamber
Work Period & Location
Daytime work 8am to 4pm, 7/22 thru 7/23:
7/22 – Cutting protruding laterals from sanitary main on 52nd & 54thSt, West New York.
7/23 – Cutting protruding laterals from sanitary main on 52nd & 54thSt, West New York.
Description of Work
Preparing sanitary main for lining
Traffic Information:
Road Closures: Police will be onsite to close the streets if needed.
Parking Restrictions: No Parking signs on both sides of the street as needed
Detours: None
Police presence: Yes
Noise/Disruptions: Sewer lining could produce some short duration noise.
We appreciate your patience and cooperation as we work to improve our infrastructure. Stay tuned for further updates!