NHSA H6/H7 Hoboken Phase 2 Construction and Traffic Management Activities: July 21st – July 25th, 2025
Project Overview
We’re continuing Phase 2 of the H6/H7 Project to enhance infrastructure reliability and improve stormwater management in Hoboken. This work will support long-term system efficiency and reduce maintenance needs.
Key Phases & Timeline
- Week of July 21st – July 25th, 2025 
- Work Locations: - 13th Street between Adams and Jefferson Streets 
- Adams Street between 14th and 15th Streets 
 
Construction Activities
- Working on louvers, pump rails, and electrical installation for the pumps at the NWRP on 13th Street between Adams and Jefferson Streets. 
- Installation of curb, curb walls and sidewalk on 15th Street, east of Adams Street. 
Traffic Management
- Adams Street between 13th and 15th Streets will be open to thru traffic one lane going northbound. 
- 15th Street will have traffic going east and westbound from Adams Street to Willow Avenue. Traffic flow will resume as normal. 
- HPD officers will be present at all intersections within work zones. 
- 24/7 no parking signs will be in place on both sides of Adams Street between 14th and 15th Streets. 
We appreciate your patience and cooperation as we work to improve our infrastructure.