Collection System Improvements Contract 4 - Week of September 21, 2025

Purpose of Project:
Rehabilitation of approximately 4,700 linear feet of combined sewers, manholes and service connection in the Cities of Union City and West New York.

Key Phases/Timeline

Sewer lining activities are expected to extend through late-October/early November.

Work Locations

  • Monday – 9/21: No Work

  • Tuesday – 9/22: Nighttime (8pm start) – Preparing sanitary mains for lining in West New York

  • Wednesday – 9/23: Nighttime (8pm start) – Preparing sanitary mains for lining in West New York

  • Thursday – 9/24: No Work 

  • Friday – 9/25: No Work

Description of Work

Preparing sanitary main for lining

Traffic Information:

  • Road Closures: Police will be onsite to close the streets if needed.

  • Parking Restrictions: No Parking signs on both sides of the street as needed

  • Detours: None

  • Police presence: Yes

  • Noise/Disruptions: Sewer lining could produce some short duration noise.

We appreciate your patience and cooperation as we work to improve our infrastructure. Stay tuned for further updates!

Next
Next

Collection System Improvements - 3 Sewer Lining Schedule Week of September 21st, 2026