NHSA H6/H7 Hoboken Phase 3 Construction and Traffic Management Activities: September 22nd – September 26th, 2025
Project Overview
The goal of the project is to reduce combined sewer overflows (CSO’s) and improve the water quality of the Hudson River. As part of the project, new storm sewer lines and curb inlets will be installed which will alleviate drainage and potential flooding issues in the northern H6 and H7 drainage basins in Hoboken.
Key Phases & Timeline
- Monday, September 22nd to Friday, September 26th, 2025 
Construction Activities:
Pipeline Crew #1:
- Grand Street between 13th Street and 14th Street - - Installation of inlets and storm piping - - Temporary re-striping 
Pipeline Crew #2:
- 14th Street between Grand Street and Clinton Street (including intersections) - - Relocation of 8" water main and other utilities - - Installation of piles, pile caps, and pipe cradles - - Installation of storm sewer pipe, manholes, and inlets 
Alternate Work Crew #2:
- Madison Street between 13th Street and 14th Street (TBD) 
- Sidewalk and Curb restoration 
Alternate Work Crew #3:
- Jefferson Street and 14th Street Intersection (TBD) 
- Sidewalk and Curb restoration 
Traffic Management:
- Grand Street between 13th and 14th Street - Road to be closed during working hours (8 am to 6 pm) 
- Roadway changed to 2-Way traffic (north and south) to allow access to resident garages. 
 - 14th Street between Grand Street and Clinton Street - Road to be closed 24 hours, 7 days/week 
 - Temporary Parking Impacts: - Grand Street between 13th and 15th Street - - Temporary no parking east of the street (6am - 6pm) - - Access to resident garages will be available during working hours and non-working hours. - Clinton Street between 14th Street and 15th Street - - Temporary no parking east side of the street, south half, from14th St to 15th St (6am - 6 pm) 
We appreciate your patience and cooperation as we work to improve our infrastructure.